Commercial building sites. Just fucked on so many levels.
I’ve seen shop fitters perform magic before, but this shopping centre is the most fucked up, behind, not my fucking job, disaster of a project I’ve seen in my 20 odd years. So many tenancies just not even remotely ready with 6 days to go. I see 30% with no plaster yet.
Pretty funny watching the senior project managers musing over the big ass cracks in the concrete slab in the main area outside Woolworths entrance. Polished concrete. Cracks running from cored holes to cored holes.
Two semi loads of goods went in this doorway the hard way because some cunt didn’t think. And of course 2 semi loads of goods comes with nooooooooo fucking packaging. My cardboard box and pallet fire in the carpark. Does that fit in the scope of waste management plan you DIDN’T tell me about.
Fuck don’t let me be dictator for a day, be some cunts with no heads.